Capital Improvement Projects

The following is a summary list of active Capital Improvement Projects within the city limits of Hoover.  As individual projects progress, their status will be updated.  As projects are completed, they will be removed from the list. 

ALL PROJECTS AS OF MARCH 20, 2023

Project Type Lead Agency Status Current Status (% 
​Complete)
Next Milestone Next Milestone (Target Date)

ROADWAYS

         
Patton Chapel Road Improvement - Modifies two existing intersections into one, in front of Gwin Elementary School. Extends sidewalk along Patton Chapel Rd.  For additional information on this project, contact Jefferson County Roads
​and Transportation at (205) 325-5141. (See More Info.)
Jefferson County Construction 95% Completion of Roadway Improvements
Spring 2023
Valleydale Rd Widening (Little) - Widens Valleydale Rd from Riverchase Pkwy to Business Center Drive
ALDOT ROW Acquisition 15% Bid Process 2024
Valleydale Rd Widening (Big) - Widens Valleydale Rd to five lanes from Caldwell Mill Rd to Hwy 280. ALDOT ROW Acquisition
​94 Total tracts
​4 Pending​
95% Utility Coordination   2023
South Shades Crest Rd, Additional Northbound Lane - Adds a northbound lane on South Shades Crest Road from Willow Lakes Drive to Hwy 150.                Jefferson County      Bid Process 90% Construction Summer 2023
Galleria Blvd Extension - County led project that extends Galleria Blvd by Chick-Fil-A to Old Montgomery Highway Jefferson County Right of Way Acquisition 80% Construction 2023
Highway 150 Right Turn Lane @ Whisperwood Lane City of Hoover Construction 95% Completion Spring 2023
Exit 9 Interchange City of Hoover/
ALDOT
Preliminary Design 15% Bid Process 2025

SIDEWALKS,GREENWAYS & TRAILS

         
Chapel Rd Sidewalks - Extend sidewalk from Matzek Drive to Park Ave.  (See more info.) ALDOT Construction
​ 
80% Completion Summer 2023
US Hwy 150 Sidewalk - Provides sidewalk on one side of Hwy 150 from Hwy 31 to Cahaba River Estates. ALDOT Design & Planning  90% Right of Way  Acquisition TBD
Alford Avenue Sidewalks - Phase 1 - Constructs sidewalks along Alford Avenue from Haden Street to Pine Lane and Haden Street from Alford Avenue to Blue Ridge Blvd. City of Hoover Final Design Stages 95% Right of Way Acquisition TBD
Oriole Drive Sidewalks - Star Lake Drive to Deo Dara Drive City of Hoover Construction 5% Completion Summer 2023
Old Columbiana Road Sidewalks - Patton Chapel Road to Green Valley Elementary City of Hoover Bid Process 20% Construction Spring 2023
Al Seier Road Sidewalks - East of Sulphur Springs Road to Ball Park City of Hoover Design Stage 95% Bid Process Spring 2023
Sulphur Springs Road Sidewalks - Preserve Parkway to Al Seier Road City of Hoover Design Stage 95% Bid Process Spring 2023
Inverness Center Drive Sidewalks - Segments from Valleydale Road to Hwy 280 City of Hoover Construction 10% Completion Spring 2023
Russet Woods Drive Sidewalks - Phase 1 - South Shades Crest Road to Guyton Road City of Hoover Construction 95% Completion Spring 2023

GENERAL / MISC

.
         
Bluff Park Pavilion City of Hoover Construction 25% Completion Summer 2023
US Hwy 31 Street Light Replacement, Phase 2 - Installs new street lighting along Hwy 31 from Patton Chapel Rd to I-65. ALDOT Construction  

95% Completion 
Spring  2023
Gwin/Simmons Traffic Signal Installation City of Hoover Construction 10% Completion Summer 2023
Hwy 31 at Hendrick/Hoover Commons Traffic Signal Upgrades City of Hoover Construction 5% Completion Summer 2023
Hoover Met at Stadium Trace Pkwy Traffic Signal Installation City of Hoover Construction 5% Completion Summer 2023
Hwy 150 at ATI Pkwy Traffic Signal Installation City of Hoover Permitting 50% Construction Fall 2023
Hwy 31 at Patton Chapel North Traffic Signal Upgrades City of Hoover Construction 5% Completion Fall 2023
Upgrade Pump Station Telemetry - Inverness & Riverchase Pump Stations - PHASE 2 City of Hoover Construction 25% Completion Winter 2023
SCADA/Telemetry For Riverchase & Inverness WWTP/Lift  Station(s) City of Hoover Construction 95% Completion Spring 2023
Upgrade Woodford Pump Station City of Hoover Construction 5% Completion Winter  2023
Applecross Pump Station Replacement City of Hoover Construction 5% Completion Summer 2023
Building 104 (#35) Lift Station (Inverness) Replacement City of Hoover Design 50% Bid Process Winter 2023
Maiden Lane - Replace double 36" CMP with 36 ft. of double 36" RCP and replace two headwalls City of Hoover Bid Process 20% Construction Summer 2023
Pavillon Drive - Replace Roadway Inlet and Stabilize Slope City of Hoover Bid Process 20% Construction  Summer 2023
South Sanders Road Dam - Lower pool elevation, lower outlet structure and spillway and replace culverts City of Hoover Bid Process 90% Construction Summer 2023